Showing posts with label TransCo. Show all posts
Showing posts with label TransCo. Show all posts

Wednesday, July 27, 2016

BWorld 73, Transco and the big beneficiaries of feed in tariff

* This is my article in BusinessWorld last July 20, 2016.


The Philippines’ expensive electricity prices in Asia -- second only to Japan -- was highlighted once again in a paper by The Lantau Group (TLG) during the Asia Clean Energy Forum (ACEF) 2016 at the ADB last June.

Metro Manila’s residential electricity prices were even higher than those in Amsterdam, Hong Kong, and Singapore, twice than those of Hanoi and Beijing, and about three times than those of Taipei and Kuala Lumpur (see chart).


This will have negative consequences for the Philippines’ bid for industrialization. Many energy-intensive sectors and big foreign companies will put up their manufacturing plants in Vietnam, Thailand, Indonesia or Malaysia, where they enjoy cheaper and stable electricity there, then export these products to the Philippines at zero tariff because of the ASEAN Economic Community (AEC). So instead of attracting more manufacturing and higher-paying industrial jobs here, our neighboring countries will snap up those jobs instead.

The quick lesson from this reality is that we should find ways to further bring down the costs of electricity here. Identify those charges, costs, bureaucratic delays, taxes and royalties that contribute to our expensive electricity, and significantly shrink or abolish them.

Unfortunately, we are not moving towards that direction.

Instead we go the opposite, by creating new measures, new indirect taxes that contribute to even more expensive electricity via the feed in tariff (FiT) scheme for renewable energy (RE) companies, among others.

The FiT scheme as designed is very anomalous for three reasons, among others: (1) guaranteed price for 20 years, (2) initial price will be adjusted upwards yearly indexed to inflation, and (3) even consumers in Mindanao, who are not connected to the Visayas and Luzon grids, do not have Wholesale Electricity Spot Market (WESM), and suffer from frequent blackouts due to insufficient power supply for, pay for FiT.

Here are the adjusted FiT rates for 2016 and the corresponding FiT payments that electricity consumers must pay to RE companies via Transco. Wind 1 and 2 and Solar 1 and 2 refer to two tiers of FiT-eligible RE firms, the second tier is given lower rate in exchange for expanding the FiT-eligible new capacity addition (see Table 1).


Last July 6, 2016, this column attempted to quantify how much the big RE companies have cornered the FiT revenues. The next day after it was published, I wrote to the National Transmission Corporation (Transco), a government corporation in charge of administering the FiT-All, and asked: (1) if my estimates of (a) P2.63 B for EDC Burgos, (b) P1.92 B for Caparispisan, (c) P0.73 B for San Lorenzo Trans Asia, etc. are correct; (2) if my estimate of P12.2 billion total FiT revenue for 2015 is correct; and (3) what are the correct numbers if those estimates are wrong.

I mentioned in my letter/e-mail that President Duterte will soon issue an EO for FoI since these are public funds collected from electricity consumers nationwide and administered by a public entity, Transco and hence, the numbers should be made public too.

Transco replied one week after and said the following:

1. My estimates of (a) P2.63 B for EDC Burgos, (b) P1.92 B for Caparispisan, (c) P0.73 B for San Lorenzo Trans Asia, etc. are “roughly higher by 10% of what has been billed to Transco by these 3 companies in 2015.”

2. My estimates of P12.2 B FiT-All for 2015 alone “are higher than the 2016 FiT-All Application levels of Transco on the basis of the following:

a. There are RE plants in the Application that have not billed Transco in 2015. Although their generation may be in 2015, these plants have not gotten the final eligibility for FiT in 2015 (processing on going). Thus, they will bill Transco only upon completion of all necessary approvals;

b. Transco also implements one month current-one month backlog billing consistent with the REPA (Renewable Energy Payment Agreement). Thus, there are plants that have gotten their FiT eligibility much later than their Commercial Operation Date (start date for FiT eligibility) and have not become current in terms of billing by the end of the December 2015 billing period;

c. Transco estimate of FiT Revenue for 2014-2015 is about P10 B. it added that although the year has passed, it has yet to accrue all amounts pertaining to 2014-2015 since the concerned REs have yet to receive their final eligibility documents/are yet to bill Transco; and

d. What has been actually billed to the FiT-All Fund for 2014-2015 energy generation is only around P8 billion.

Thank you Transco for the reply, which allows me to construct new estimates of FiT revenues per company (see Table 2).


The 12.40 centavos/kWh FiT rate granted by ERC in February this year will soon be revised upwards because it was just a provisional order.

Forcing electricity consumers to pay more expensive electricity from new renewables is wrong. Consumer choice is compromised or killed. If people really believe that the new renewables’ costs are indeed falling and attaining grid parity with coal and natural gas, then they should support the abolition of RE law of 2008 or RA 9513. This way, RE developers can sell electricity to willing customers without any guilt or embarrassment.

Bienvenido S. Oplas, Jr. is a Fellow of SEANET and Stratbase-ADRi, and head of Minimal Government Thinkers.
---------------

See also:

Saturday, July 09, 2016

BWorld 70, Wind power firms corner billions of FIT money

* This is my article in BusinessWorld last Wednesday.


From an introductory price hike of 4.06 centavos/kWh of Feed In Tariff Allowance (FiT-All) in 2014, this subsidy scheme of guaranteed price for 20 years became 12.40 centavos/kWh in 2016. As more renewable energy power plants are added to the country, the cost of FiT-All will keep rising and it is safe to assume that this FiT-All might further rise to 20 centavos or more by 2017. And even consumers in Mindanao who are not participants of the Wholesale Electricity Spot Market (WESM) are paying for this.

Such is the abuse received by consumers nationwide via expensive electricity from subsidies to renewable energy (RE) companies. Last month, I wrote to the National Transmission Corporation (TransCo), a government corporation in charge of administering the FiT-All, and asked who among the RE developers received how much.

TransCo sent me a statement of cash flow, Receipts minus Disbursements = Fund Balance, and Fund Payable as of end-2015. I thanked them for the reply but that was not the information that I needed, so I called up the officer and asked why the list of who received how much was not sent. She said that they cannot release it to the public, implying confidentiality of the information. I wish that President Duterte will release that new Executive Order on Freedom of Information (FoI) very soon. The Department of Budget and Management (DBM) releases yearly data on how much government agencies received from taxpayers so why can’t TransCo release data on how much RE developers received from electricity consumers nationwide?

Last month, the Department of Energy (DoE) posted on its Web site the “List of Renewable Energy (RE) Plants with Certificate of Endorsement (CoE) to Energy Regulatory Commission (ERC) for Feed-in Tariff (FiT) Eligibility” as of June 20, 2016. My first question as to which RE companies received FiT has been answered. There are some RE developers who did not receive FiT.

By virtue of their enormity (MW capacity) compared to other RE developers, these companies are the potential main beneficiaries of expensive electricity policy provided by the RE Act of 2008 (RA 9513):

1. Burgos Wind Power Project (Phases 1 and 2) by EDC/Lopez group, 150 MW at P8.53/kWh

2. Caparispisan Wind Power Project by North Luzon RE Corp./Ayala group, 81 MW at P8.53/kWh

3. San Lorenzo Wind Power Project by Trans-Asia RE Corp./PHINMA group, 54 MW at P7.40/kWh

4. Pililla Wind Power Project by Alternergy Wind One Corp./Vince Perez, 54 MW at P7.40/kWh

5. Nabas Wind Power Project by PetroWind Energy, Inc., 36 MW at P7.40/kWh

6. Bangui Bay Wind Power Project Phase 3 by Northwind Power Development Corp./partly Ayala, 19 MW at P8.53/kWh

7. Cavite EcoZone Solar Power Project by Majestics Energy Corp., 41.3 MW at P9.68/kWh.

I only need to find out the answer to my second question: how much did other RE companies receive each? I went to the Energy Regulatory Commission (ERC) Web site and saw ERC Case No. 2015-216RC, the TransCo petition for FiT-All for 2016. The important factors and ingredients were there, so I began making my own estimates.

The FiT rates and installed capacity in MW for all RE developers already given by the DOE, I used the following factors and assumptions to construct a table of estimates.

a. Capacity factor -- derived using TransCo filings with ERC which are per technology basis.

b. Generation (MWh) -- derived from the capacity factor.

c. FiT Revenue -- FiT rate multiplied by the generation.

d. FiT Cost Recovery Revenue (FCRR) -- the amount that the RE firm got from WESM or the distribution utility (DU). This is derived using the average WESM rate per TransCo application to ERC. This amount may not be that accurate since the time of dispatch will not result to the average price.

e. FiT Differential (the basis of FiT-All) = FiT Revenue minus FCRR. For some power sources like wind plants, the calculated FiT Differential here may be under estimated since wind usually blows during off-peak hours period, and WESM prices are then below the average rate (see table).


Now these are just estimates and there could be some corrections or mistakes in the last four columns on the right, even in the capacity factor. The capacity factor is not constant or flat the whole year, some months and days are more windy than others, and some months and days are more cloudy than others and hence, affect the output of solar PV.

I wish to be corrected by TransCo if those numbers are wrong, perhaps they should release the correct numbers. Is it true that the Lopez and Ayala groups cornered nearly P5 billion from FiT in 2015 alone? The other companies like Trans-Asia/PHINMA, Alternergy, Hedcor/Aboitiz, they also enjoyed perks by several hundred millions of pesos each because of the unjust system of high, guaranteed price system under FiT.

On a related note, it is good that Mindanao does not have any of those expensive and pampered solar and wind plants that are primarily responsible for more expensive electricity in the country. Mindanao has more hydro, big hydro with no FiT and run of river hydro with small FiT of P5.90/kWh. Recently, Mindanao added more coal plants, which is the right thing to do. Stable, dispatchable, non-intermittent and cheaper coal power, that is what Mindanao and the rest of the country should have if we are to sustain fast growth. The move by the new DENR Secretary for anti-mining policy will adversely affect coal mining and coal power development in the country. This policy move should be checked and discontinued.

Bienvenido S. Oplas, Jr. is a Fellow of SEANET and Stratbase-ADRi, and head of Minimal Government Thinkers.
-------------

See also: 

Saturday, May 21, 2016

Energy 66, What companies receive FIT and by how much?

May 19, 2016.

This is the subject of my letter to the National Transmission Corporation (TransCo) last Monday. TransCo is a government corporation that owns all the transmission assets of the government. Among its five key responsibilities is to administer the Feed-in-Tariff Allowance (FIT-All) Fund for renewable energy (RE) generators. Its website clearly and proudly discusses the FIT system and why it is "good" for electricity consumers because of its "merit order effect".

I wrote to their customerservice@transco.ph early morning of May 16, 2016:

Dear Sir/Madam,

I would like to request for data on (a) list of RE companies that have received FIT, 2015-2016, (b) how much each company received, (c) total FIT payment, (d) related data that you may want to share.

I will use the data for a research paper that I am writing for our think tank, Minimal Government Thinkers, which I hope to send you and the DOE a copy, and a short version for my column in BusinessWorld. I assume these are public data as the money collected is taken from electricity consumers nationwide.

Thank you very much and I hope to  hear from you.


Sincerely,

Bienvenido "Nonoy" Oplas, Jr.
President, Minimal Government Thinkers, Inc.
Fellow, South East Asia Network for Development
Fellow, Stratbase-Albert del Rosario Institute (ADRi)
Columnist, BusinessWorld, My Cup of Liberty

I did not get any reply. I followed it up with another email  yesterday morning,

Hi,

I would like to ask if you can share this data with me.
Thank you very much.

Sincerely,

Bienvenido Oplas, Jr.

Still no reply. Ahh, this must be among their "top secret" data perhaps? One problem with the absence of a Freedom of Information (FOI) law or Exec. Order is that certain government offices can only collect-charge-bill-fine us ordinary people and when we ask where the money went to, they can only give one standard reply, the Sound of silence.

Anyway, I saw this report in Business Mirror the other day, among the numbers reported there: 

"FiT subscriptions for RE resources have significantly increased to 806.82 megawatts (mW) from 646.65 mW installations since the start of 2016. The following are the FiT subscriptions to date: Biomass has 11 power plants with a total capacity of 94.25 mW; hydro has four accounting for 26.6 mW; wind has six accounting for 393.9 mW.

Meanwhile, as of March 15, 2016, the DOE issued Certificates of Endorsement for FiT Eligibility (COE-FiT) to 11 solar-power plants accounting for 292.07 mW to the Energy Regulatory Commission (ERC). More solar-power projects may be issued COE-FiT at the completion of the ongoing validation and assessment of the submissions received by the DOE in relation to the March 15 deadline for the expanded FiT for solar-power projects."

So, as of March 15, 2016, DOE issued COE-FiT for the following installations:

* Wind with six power plants, 393.9 MW,
* Solar with 11 plants, 292.07 MW, 
* Biomass with 11 plants, 94.25 MW,
* Hydro with four plants, 26.6 MW,
Total  806.82 MW.

I just want to know who are those 6 wind plants, 11 solar plants, etc. and how much did they get from the 4.06 centavos/kWh that we consumers paid to them from February 2015 to March 2016. The FIT has been raised to 12.40 centavos/kWh starting April 2016. 

Expensive electricity is lousy. Making it even more expensive with extra charges like FIT-All is lousier. And when we ask who are these companies that receive the extra charges, the answer is a Sound of silence. 

Hi TransCo, I still hope to receive a reply from you. I hope to write another paper about you soon, whether you give a reply (and some data) or not. You will receive this blog post via email, fb, twitter, etc. Three of your Board Members are Cabinet Secretaries -- DOF, DOE, DENR. They all have twitter accounts. Thank you.

May 21, 2016.

Today, I received a reply from Transco, they sent me two tables, the FIT-All cash flow and fund payables as of end-December 2015. They also gave me the name of the person I should talk to, the office local tel. no.



Thank you Transco. I still need the list of companies that received and about to receive the FIT-All. I will call next week.
-----------------