--------
With the debate on whether the power generation rate
increase -- mistakenly referred to as "Meralco rate hike" -- is
justified or not, the role of WESM has been put under question.
The Wholesale Electricity Spot Market was created under
Sec. 30 of Republic Act 9136 or the Electric Power Industry Reform Act of 2001
(EPIRA). Power generators, distribution utilities (DUs) and electric
cooperatives, bulk consumers, similar entities authorized by the Energy
Regulatory Commission (ERC) can participate there.
Below are some allegations or criticisms about WESM:
1. DUs or electric cooperatives like Meralco
collude with certain power generators and bid up the price at WESM.
2. DUs and bulk consumers can easily buy forward
contracts or buy electricity for specified short periods in the future to cover
any foreseen exposure they may have. This is on top of their long-term
bilateral contracts with power generators.
3. DUs who buy at WESM would know who supplied them
power at any time, any day.
4. It is “a misnomer, a huge farce: More than 90
percent of its transactions aren’t spot trading transactions at all. They are
bilateral contracts, with the price and quantity not having anything to do with
market conditions at any given time.”
5. The rule that WESM “must offer all available
electricity capacity to the spot market” is mocked and disobeyed by many power
companies by offering the maximum bid of P62 per kilowatt-hour (kWh).
6. WESM and its high rates in the November-December
period could have been bypassed by running the state-owned Malaya power plants.
How true or valid are these allegations? Let us tackle
each of them -- with hard data.
1. The allegation of collusion between some DUs
like Meralco and power generators is belied by the average generation cost in
2013 -- P5.52 per kWh – which was lower than the P5.76 in 2012. The
spike in the December billing – which was based on the November generation cost
-- was mainly due to the absence of cheaper natural gas from Malampaya, and the
purchase of more expensive power from diesel plants, so that brownouts would be
avoided.
To prove “collusion,” one must show who colluded. Barring
this, collusion is simply an allegation. Item number three below will
illustrate why identifying who colluded is impossible.
2. DUs and bulk consumers can buy or contract
electricity at WESM – say about 10 percent of their projected demand -- just
one or two hours ahead, not weeks or months ahead. There is an
allowance if some of its contracted generator plants will conk out or suffer
output reduction due to mechanical problems, or the demand would suddenly go
up. It is a spot market and as such is characterized by price volatility.
But at least power supply is delivered, and disruption or a brownout, is
avoided. When supply exceeds demand by a wide margin, the price goes down. When
this margin narrows, the price goes up.
Here is a short history of WESM prices from July 2006 to
November 2013. The three outliers, January 2009 – when prices were very low --
and February-March 2010 and November-December 2013 – when prices were very high
-- are explained in bold sentences. Note the lower cost of WESM load-weighted
average price (LWAP) compared to average Napocor rates.
3. Knowing who sold power and by how much at
WESM is fungible. When you buy, you no longer know from which plant
and how much power is coming, so there is no way Meralco or ERC can know.
Suppose there are 10 generators (excluding those covered by bilateral contracts)
supplying WESM in a given hour, and there are 60 buyers (excluding those
covered by bilateral contracts) during the same hour, it is impossible to
attribute to one generator any output bought by a buyer.
Take this case. On December 6 -- or two days before
Typhoon ‘Yolanda’ struck Eastern and Central Visayas -- coal and hydro plants
could produce less than 5,000 MW in Luzon, while demand stood at 5,400 MW. More
than 3,200 MW of power were either on planned/scheduled shutdown or on forced
outage. The oil/diesel plants provided the power to address demand that coal
and hydro could not supply. But the supply came at a higher price, in exchange
for no brownout that day in Luzon.
Knowing which among the various oil-based power plants
supplied how much energy to different DUs and bulk consumers at different
prices at different hours of the day cannot be determined. DUs decide whether
to buy at that particular price that hour, or beg off on those hours and suffer
brownouts in certain cities and municipalities of their franchise area.
4. On the notion that bilateral contracts, not
spot trading, rule WESM, a friend from the power generation sector sent me
this observation:
“There used to be a limit of 90 percent on bilaterals,
which was designed to ensure that some transactions were left to the spot
market, but only for the first five years of the WESM (expired 2011). Now
there is no limit other than the mandate that all distributors source their
generation at the least cost for the captive market. WESM pricing is very
volatile and most utilities do not want the volatility and will contract most
if not all of their requirements, sourcing only the imbalances from the spot
market.
“The imbalances tend to happen at peak hours, since
Meralco should ordinarily have enough bilateral contracts to cover their
baseload and even intermediate needs. This means they are buying from
WESM at the peak hours so their cost will be higher than the average WESM (the
33/kWh November 2013 vs 11/kWh that Bobi Tiglao was talking about). This is not
necessarily bad, since the rest of the time Meralco was buying from their
bilateral contracts at prices that in November (for Dec generation bill) ranged
from P3.75 to P9.97 (the P9.97 I believe included the alternative fuel cost by
previously nat-gas running plants).”
Here are the day-by-day power plant shutdowns from late
October to early December 2013.
As shown in the above chart, the combination of scheduled
outages (especially by cheap natural gas-running plants) and of unscheduled or
forced outages (especially by coal plants that are second-cheapest next to
natural gas) resulted in power under-generation. The power deficit can be
supplied by the more expensive peak-load oil plants. DUs like Meralco then had
only two options: buy from these more expensive power plants, or beg off and
have rotating brownouts while keeping the old rates for billing customers.
When people curse even a half-hour brownout, or are
willing to buy gen-sets running on expensive oil, that shows their
unwillingness to suffer brownouts and their readiness to pay higher for
electricity. Unfortunately, some are unwilling to divulge that much by going to
the streets or taking their cause to the media or the Supreme Court.
5. On abusing the P62/kwh maximum bid price, the
same friend observed that a DU like Meralco could possibly have contracted more
standby capacity and assume capacity cost even if the plants are not
running. This pricing tradeoff will determine its maximum bid price in
the spot market.
Here is an illustration using hypothetical numbers.
Suppose a 1 kW diesel peak-load plant has the following costs:
(a) Annual fixed costs (capacity + fixed operations and
maintenance (O&M)) = P12,000
(b) Total potential annual operating hours less 10
percent downtime = (365 days) x (24 hours/day) x 0.9 = 7,884 hours
(c) Fixed cost = (a)/(b) = P1.52/kWh
(d) Variable costs (fuel, lubricants, variable
O&M) = P12/kWh
(e) If operated at maximum number of hours, unit cost is
(c) + (d) = P13.52/kWh
If it only operates 10 full days a year equivalent (5
hours/week x 49 weeks, 3 weeks for holiday + maintenance shutdown), then
(f) Fixed cost = (a)/(24 hours/day x 10 days) = P50/kwh
(g) Unit cost = (f) + (d) = P62/kWh, maximum bid price.
Even on a weekend and on the day that Typhoon Yolanda
struck central Philippines, electricity demand was high. Should be due to many
Christmas parties and reunions, some factories, the malls and tiangge that
were open until late evening, not to mention the many night markets sprouting.
When a power company bids the P62/kWh maximum price in
WESM, it does not mean that it automatically wants to abuse a particular
situation of extra high demand relative to power supply at a particular hour of
the day. WESM, as mentioned above, has a rule that power generators must “offer
all output” to the spot market.
If a power plant with, say 100MW capacity, needs to slow
down one or two turbines to prevent a possible unscheduled or forced shutdown
the next day due to some mechanical troubles, what it does is to bid, say zero
to P1/kWH, for the first 25 MW (this means automatic dispatch of their power
supply, so they can fulfill their power contract to a particular DU).
Then bid P4 for the next 25 MW, P7 for the next 25 MW,
and P62 for the last 25 MW. This is deliberate “pricing out of the market” so
that no one will buy the last 25 MW and will allow the plant operator to check
and correct any mechanical problems, thus the bigger problem of the entire 100
MW plant shutting down later that day or the next few days will not happen.
6. On running the state-owned Malaya power plants,
chart 4 above shows that Malaya 1 had been on maintenance shutdown between July
until early December, while Malaya 2 was similarly shut down from late October
to early December. Even if the Department of Energy (DOE) ordered the plants to
run on expensive diesel fuel, they won't run. Reserves were really thin or
tight in the November-December period because of the confluence of planned and
unplanned shutdowns of several big power plants.
Looking forward, this chart from Energy Secretary Jericho
Petilla depicts the power demand-supply outlook as of August last year:
If the projected demand (if not higher) comes to pass,
brownouts are going to happen in Luzon by April-May 2015. The chart also shows
that for the April-May period this year, reserves will be very thin but
sufficient to provide power, assuming not one of those big power plants will
suffer from unscheduled shutdowns. For power plants that are 20 years or older,
this assumption is likely to happen.
That is why during the peak summer months, limited
brownouts in Luzon are likely to happen. And many people will complain again --
when electricity rates go up, when costlier electricity is not provided in
exchange for brownouts.
What are the lessons from this debate?
1. WESM works. The spot market is real, not a farce or
rigges as suggested by some conspiracy theorists. The spot market has supplied
uncontracted or excess demand by DUs and uncontracted excess supply by power
generators. But WESM prices – as in any electricity spot market anywhere in the
world -- are very volatile and unstable.
2. Price volatility in the spot market is the tradeoff of
power supply-demand volatility and uncertainty. Peak load power plants were
invented mainly to plug this short-term (a few hours per day) power deficit,
and there is a premium for such short-term use and supply of power, which
prevents brownouts.
3. Power generation price hikes were due to overlapping
maintenance or scheduled shutdown and forced or unscheduled outages, especially
of several power plants running on cheap natural gas and coal, particularly
from late October to early December last year.
4. Such power generation rate hikes are a necessary evil.
They are bad but having rotating brownouts, buying expensive gen-sets running
on expensive oil, or enduring candles at night and risking fire, are equally
bad, if not worse. The rate hike should have been temporary, only for December
2013 and January 2014, with the old rates resuming next month. With the Supreme
Court temporary restraining order (TRO) on the rate hike, the debate on
politicized electricity pricing will extend until March-April, if not beyond.
5. Allegations of collusion in WESM between DUs like
Meralco and power generators are just allegations. It is not possible to
pinpoint who supplied how much to whom at different prices at different hours
of the day. It is also not possible to suddenly contract power for succeeding
weeks or months at the spot market. The lead time is only one or two hours, not
one or two weeks or months.
6. To prevent or minimize this occasional politicized
electricity pricing involving not only the DOE, ERC and Congress, but
even the Supreme Court, there should be (a) more power plants, the reliable
ones running on cheap energy sources like natural gas, geothermal and coal, and
(b) proper or better maintenance of existing ones, especially those that are
above 20 years old.
7. To bring down electricity costs, government taxes,
fees and royalties should significantly shrink and decline. The value added tax
(VAT) should also not apply on system loss charges, unless there is a zoombie
value deducted tax (VDT) because system loss is electricity deducted from additional
supply to consumers.
8. To add more power plants, especially cheap energy
sources like natural gas and coal, government bureaucracy, permits, regulations
and prohibitions should significantly shrink and decline. Some permits should
be collapsed or abolished.
9. Hydro is also cheap. To have more hydro power plants,
there should be more dams. Global cooling means more rains, more flood, more
water every year, not less. The excess rainwater and flash flood should be
impounded by more dams, in turn producing more hydro power. After producing
hydro power, the excess water can be used for drinking (after being purified of
course) or irrigation.
See also:
Fat Free Econ 49: Growth Amid Storms, December 03, 2013
Fat Free Econ 50: Growth, Bubbles and the PH Economy, December 19, 2013
Fat Free Econ 51: Ten Things About the Meralco Rate Hike, December 28, 2013
Fat Free Econ 52: Optimism in 2014, January 02, 2014
Energy Econ 10: Climate Alarmism and FIT for Renewables, June 28, 2013
Energy Econ 11: On the Power Rate Hike, January 17, 2014
No comments:
Post a Comment